NOTIFICATION
Sachivalaya, Gandhinagar, Dates the 22nd
October, 2003.
THE GUJARAT ELECTRICITY INDUSTRY (REORGANISATION
AND REGULATION) ACT, 2003.
No. GHU-2003-53-GEI-11 -2003-3898-K: In exercise of the
powers conferred by sub-clause (e) and (j) of sub section
(2) of section 64 read with section 31 of the Gujarat
Electricity Industry (Reorganization and Regulation)
Act,.2003 (Guj.24 of 2003) the Government of Gujarat hereby
makes the following rules regarding the information to be
furnished relating to establishment, acquisition, extension
or replacement of a generating station, namely :-
1
Short title, extent and commencement.- (1)
These rules may be called the Gujarat Electricity Regulatory Commission
(Generating Station Information) Rules, 2003.
(2)
They shall come into
force on the date of their publication in the
Official Gazette.
2
Definition:
In these rules, unless the context
otherwise requires, -
a) "Act" means the Gujarat
Electricity Industry (Reorganization and Regulation)
Act, 2003 ;
b) "Commission" means the Gujarat
Electricity Regulatory Commission established under
the
Act.
c) "Form" means form appended to these
rules.
3
Furnishing of Information relating
to establishment, acquisition, extension or
replacement of generating station.- (1) Any
person who establishes a generating station or
acquires a generating station or extends or replace
major Unit of Plant or works pertaining to
generation of electricity in the generation station
shall furnish the information relating to such
establishment, acquisition, extension or
replacement of the generating station in Form I
to the Secretary to the Government of Gujarat,
Energy and Petrochemicals Department and to the
Commission.
(2)
Such information shall
be furnished within fifteen days of the
establishment, acquisition, extension or
replacement of the generating station.
4
Furnishing of
information relating to generation plan, shut down
or break down of the plant.-
The generating company
shall furnish the information relating to the
generation plan, shut down proposed for planned
maintenance, break down of the Plant and other
factors affecting the generation and supply of
electricity in Form II to the Secretary to
the Government of Gujarat, Energy and Petrochemicals
Department, to the Commission and to the Licensee
of the area where the plant is situated.